Overview
The Petrojam
Kingston Refinery upgrade/modernization project has been developed based on the
results of a pre-feasibility study that was carried out on Petrojam’s behalf by
Muse Stancil which investigated a number of possible plant upgrade options. Based on an assessment of the various options studied
it was decided to upgrade the refinery in two phases as outlined below.
PHASE
1
Expand the refinery
crude capacity from 35 kbbls/day to 50 kbbls/day to better meet local
market demand and to achieve competitive economies of scale.
- Installation of a new
catalytic reforming unit with increased capacity (7,500 kbbls) capable of
supplying the full gasoline demand of the Jamaican market.
- Installation of a new
vacuum tower (nominal capacity 30 kbbls/day).
- Installation of a
Visbreaker Unit (15kb/d) for the production of a lower cost heavy fuel oil
product.
- Installation of new desulphurization
facilities to reduce the sulphur content in diesel oil from 5000ppm to
around 15ppm.
The estimated cost for the Phase I program is US$ 200 million.
PHASE 2
- Installation of a bottoms
upgrading scheme to reduce the proportion of atmospheric bottoms in the
overall refinery production slate using a delayed coker technology.
Depending upon financing and capital considerations it may be decided to
implement Phase 2 as a separate project. Export of vacuum gas oil will
continue.
The estimated
capital cost for the Phase 2 program is estimated at US$ 250-300 million
depending upon the final conversion scheme chosen.
Why Upgrade?
The Refinery’s
present production technology obliges Petrojam Ltd. to use more expensive,
light crude oils and spiked crude oils (crude
oils mixed with semi-refined distillate products) in order for the
production mix to match the domestic demand pattern. Finished products are also
imported to supplement deficit production or as refinery economics dictate.
The current
refinery design is a hydroskimming configuration with a small catalytic
reformer for producing high-octane gasoline blending components. Approximately 56%
of the refinery’s production is heavy fuel oil with the remaining 44% being
‘clean’ products (LPG, Turbo, Gasoline and Diesel).
This technical limitation restricts the long-term competitiveness of
the refinery versus other competing refineries in the region, which produce a
higher percentage of higher value ‘clean’ products.
Future Challenges
Some future
challenges that face the refinery include:
The push for lower sulphur
petroleum fuels (gasoline and diesel oil) in order to protect the
environment and to be more compatible with new vehicle engine types;
- A shift to diesel
powered engines due to their higher efficiency and more acceptable
environmental impact;
- The planned
introduction in the medium term (2009+) of new fuels types such as LNG or
coal;
- The planned phase-out
of MTBE in gasoline;
The
challenges facing the refinery can only be addressed with a strategic decision
to upgrade its production facilities through the inclusion of a bottoms
upgrading facility. At present the plan is to implement the PHASE 1 program
only.
Milestones
The projected schedule and
principal milestones for the development of the Petrojam Refinery Upgrade
project is as follows:
- Execution
of the Basic Engineering Phase = Feb 2000 – Jan 2007
- Completion
of Environmental Impact Assessment Study = Dec 2006
- Development
of Financing Plan /Arrangement of Debt & Equity Financing = Jan 2007
- Construction
Phase = First Quarter 2007 – Second
Quarter 2009
- Plant
Startup = Mid Year 2009
PDVSA
Partnership
The national Oil Company of Venezuela,
under the Petrocaribe Agreement, has indicated a strong interest in
participating in the proposed expansion/upgrade of the Petrojam Refinery. They
have suggested that they would be willing to consider taking an equity position
in the upgraded refinery and in providing Technical assistance to Petrojam in
the Project Development effort.
back to top
|